Timeline
EP PETROECUADOR
Request for Information No. 1
Liquefied Natural Gas Imports
RFI Timeline
LNG Import Project under DPU Terms
Response Submission Deadline
Key milestones and indicative dates for the RFI.
4 key milestones
-
Launch
RFI Publication and Issuance
Formal launch of the market consultation.
-
Participation
14 – 30 Sept. 2026Questions and Comments Period
Period for participants to submit questions and comments.
-
Clarifications
Responses and Clarifications
EP PETROECUADOR will address the questions received.
-
Closing
RFI Response Submission Deadline
Scheduled final date for submission of RFI responses.
The dates shown reflect the indicative RFI schedule.